Worker deaths expose corporate safety negligence
By
Larry Hales
Denver
Published Oct 18, 2007 11:09 PM
Five workers died on Oct. 2 when vapor from a solvent they mixed with an epoxy
to coat a pipe at a pumped storage plant near Georgetown, Colo., was ignited
and caught on fire due to malfunctioning equipment.
The plant is owned by Xcel Energy, though the men were contracted to Xcel
through RPI Coating (Robison-Prezioso Inc.), based in California, where all the
men were from.
RPI began the job in early September after cracks were found in the concrete;
the work was slated to end in November. The 4,050-foot-long pipe is used to
pump water from an upper reservoir to a lower reservoir, which turns turbines
that create electricity, and later the water is transferred back to the upper
reservoir.
On the day of the tragedy nine men were inside the pipe and two outside. Their
difficult job entailed sandblasting the concrete and then spraying the epoxy on
the twelve-foot-wide pipe.
The epoxy is held in a hopper that keeps it warm so that it can pass easily
through a sprayer. The solvent methyl ethyl ketone (MEK) was added to thin the
epoxy when it began to thicken.
According to the Environmental Protection Agency, MEK is toxic; acute exposure
can lead to irritation of the eyes, nose and throat and can produce nausea and
headaches. MEK is flammable, heavy and its vapors can travel far in enclosed
areas.
According to four of the nine-man team that was 1,400 feet from the lower end
of the tunnel, the fire started at around 2 p.m. Survivor Eric Thomas,
interviewed by the Denver Post, said: “When it flashed, it was just lucky
if you were on the right side of the fire. ... It’s like nothing
I’ve ever been through in my life.”
The five men that died were on the other side of the white hot fire and had to
flee toward the upper end of the pipe, as the other four ran towards and out of
the only accessible entrance/exit.
The Denver Post describes the scene, as reported by survivors to Carolynn
Dejaynes, wife of one of the victims. “Flames from the spraying machine
were leaping onto Donnie Dejaynes’ sleeves as he tried to shut off a
valve on the sprayer, Carolynn Dejaynes said. ... Dejaynes was yelling for the
other men to get fire extinguishers, she said. Although they found a few, the
extinguishers were useless because they did not have the type of foam that puts
chemical fires out.”
Dejaynes “patted a fire out that was burning his clothes and retreated
with the four other victims up the tunnel, his wife said. They were trapped
where the tunnel takes a steep rise.”
The men were not given oxygen for two and a half hours after the fire started,
until it was too late and the men had probably already died. The last
communication with the men was around 3:30 p.m. The breathing apparatuses were
lowered at 4:30 p.m. and fans were not reversed to draw out the smoke until
5:30 p.m.
Though RPI Coating, Inc. and Xcel both have expressed sympathy for the deaths
of the workers, the phony gestures ring hollow as the conditions under which
the workers toiled are revealed.
Democratic Governor Bill Ritter’s exclamations of a
“thorough” investigation mean very little as well, as early in his
first term he vetoed a bill that would have eliminated one of two votes needed
to win union recognition.
Family members question the conditions of the tunnel. Some told the Denver Post
that the men’s supervisor told them not to enter the tunnel the day
before the accident because it was unsafe.
There was only one feasible way out of the tunnel and no escape ladders on the
upper end. The accessible exit was at the lower end of the tunnel. The men that
died were above the fire and their attempts to escape were thwarted by a
slippery incline.
The Oct. 2 deaths are not the first for RPI. According to the Occupational and
Safety Health Administration (OSHA), a worker was crushed to death on the San
Francisco Bay Bridge in 2002 when scaffolding collapsed. And in 2001, a paint
containment panel that was inadequately secured on the same bridge fell on a
passing motorist, killing the person.
In fact, OSHA has noted six violations by RPI within the past seven years. From
1990 to 2000 there were 33 violations, though the company only paid $12,000 in
fines. Within the last five years, RPI has been made to pay $64,000 in
fines.
In 2001 a worker fell more than 80 feet from a platform. It was found that
employees were not properly trained to use harnesses. Nine employees in 2000,
and one in 1998, were found to have highly toxic levels of lead in their blood.
California OSHA found that the company had not provided proper filters in their
respirators. (Denver Post, Oct. 3)
The deaths at the Xcel plant could have been avoided had simple precautions,
such as an escape route out of the tunnel, been provided. And while RPI, with
its numerous violations, is to blame, so is Xcel—which operates some of
the dirtiest power plants in Colorado, Texas and Minnesota and has engaged in
market manipulation to increase revenue.
A fact sheet on eronwatchdog.org states: “Investigators have targeted
Xcel Energy as part of the federal probe into California’s failed
wholesale electricity market and possible price manipulation. Investigators
found that traders at Xcel Energy and Mirant discussed ‘games’ to
profit from California’s electricity crisis in 2000, including schemes to
schedule nonexistent power use and to take advantage of
‘congestion’ payments on California’s overburdened electric
grid.”
Ultimately, though, it is the capitalist system and the two parties that do its
bidding that are to blame, for it is the system that cares nothing for
workers’ safety. Its lackey politicians that refuse to take any necessary
measures to prevent tragedies like the one at Xcel are to blame.
Articles copyright 1995-2012 Workers World.
Verbatim copying and distribution of this entire article is permitted in any medium without royalty provided this notice is preserved.
Workers World, 55 W. 17 St., NY, NY 10011
Email:
[email protected]
Subscribe
[email protected]
Support independent news
DONATE